[petsc-dev] petsc release plan for march 2021

Satish Balay balay at mcs.anl.gov
Sun Mar 28 13:57:55 CDT 2021


Perhaps I should not have kept a weekend deadline here.

Lets use 'freeze': 'March 29 (Mon) 5PM CST' - but retain the release date 'March 30 5PM EST (we have March 31 - if needed)

Satish

 On Sun, 28 Mar 2021, Satish Balay via petsc-dev wrote:

> A reminder!
> 
> Satish
> 
> On Tue, 9 Mar 2021, Satish Balay via petsc-dev wrote:
> 
> > All,
> > 
> > Its time for another PETSc release - due end of March.
> > 
> > For this release [3.15], will work with the following dates:
> > 
> > - feature freeze: March 28 say 5PM EST
> > - release: March 30 say 5PM EST
> > 
> > Merges after freeze should contain only fixes that would normally be acceptable to release workflow.
> > 
> > I've created a new milestone 'v3.15-release'. So if you are working on a MR with the goal of merging before release - its best to use this tag with the MR.
> > 
> > And it would be good to avoid merging large changes at the last minute. And not have merge requests stuck in need of reviews, testing and other necessary tasks.
> > 
> > And I would think the testing/CI resources would get stressed in this timeframe - so it would be good to use them judiciously if possible.
> > 
> > - if there are failures in stage-2 or 3 - and its no longer necessary to complete all the jobs - one can 'cancel' the pipeline.
> > - if a fix needs to be tested - one can first test with only the failed jobs (if this is known) - before doing a full test pipeline. i.e:
> >    - use the automatically started and paused 'merge-request' pipeline (or start new 'web' pipeline, and cancel it immediately)
> >    - now toggle only the jobs that need to be run
> >    - [on success of the selected jobs] if one wants to run the full pipeleine - click 'retry' - and the remaining canceled jobs should now get scheduled.
> > 
> > Thanks,
> > Satish
> > 
> 