[petsc-dev] PETSc 3.10: September 4, 2018, is the cutoff-date for new features
Satish Balay
balay at mcs.anl.gov
Wed Sep 12 09:36:53 CDT 2018
Sorry - I've started the tarball creation process - so this change would have to be queued for 3.10.1
Satish
On Wed, 12 Sep 2018, Richard Tran Mills wrote:
> Hi Satish,
>
> Can I add a line about the new AIJSELL Mat type to the changes list before
> you do that? Meant to do that but didn't get around to it yesterday.
>
> --Richard
>
> On Wed, Sep 12, 2018, 6:00 AM Balay, Satish <balay at mcs.anl.gov> wrote:
>
> > All release relevant PRs are now merged to master. And I'm ready to tag
> > the release [and spin the tarballs]
> >
> > Any potential (code, doc) fixes can be queued for 3.10.1
> >
> > Satish
> >
> > On Tue, 11 Sep 2018, Satish Balay wrote:
> >
> > > Reminder!
> > >
> > > please check
> > > http://www.mcs.anl.gov/petsc/documentation/changes/dev.html and update
> > > src/docs/website/documentation/changes/dev.html with relavent changes.
> > >
> > > Thanks,
> > > Satish
> > >
> > > On Mon, 10 Sep 2018, Satish Balay wrote:
> > >
> > > > Also - please check and update
> > src/docs/website/documentation/changes/dev.html as needed.
> > > >
> > > > Thanks,
> > > > Satish
> > > >
> > > > On Wed, 5 Sep 2018, Karl Rupp wrote:
> > > >
> > > > > Dear PETSc developers,
> > > > >
> > > > > please open any outstanding pull requests for the upcoming PETSc
> > 3.10 release
> > > > > in the next few hours. After that, please do not merge anything to
> > `next` or
> > > > > `master` unless it is integration work for existing open PRs.
> > > > >
> > > > > You can open up new pull requests in the next days and weeks as
> > usual. If
> > > > > these are documentation enhancements, we will most likely integrate
> > them
> > > > > quickly. If these are bugfixes, we may still integrate them for
> > PETSc 3.10,
> > > > > decided on a per-case basis. New features, however, will not be
> > integrated
> > > > > until PETSc 3.10 is out.
> > > > >
> > > > > Thanks and best regards,
> > > > > Karli
> > > > >
> > > > >
> > > > >
> > > > > On 08/30/2018 06:09 PM, Karl Rupp wrote:
> > > > > > Dear PETSc developers,
> > > > > >
> > > > > > this is a gentle reminder for the cutoff-date on September 4.
> > > > > >
> > > > > > Best regards,
> > > > > > Karli
> > > > > >
> > > > > >
> > > > > >
> > > > > > On 07/27/2018 02:41 AM, Karl Rupp wrote:
> > > > > >> Dear PETSc developers,
> > > > > >>
> > > > > >> in order to ensure a PETSc 3.10 release no later than by the end
> > of
> > > > > >> September (possibly earlier), we agreed on September 4, 2018, as
> > the
> > > > > >> cut-off date for new features. Please make sure that a pull
> > request has
> > > > > >> been opened on Bitbucket by this time. This is the preferred
> > model over
> > > > > >> merging to next directly, since our Jenkins test infrastructure
> > will test
> > > > > >> each PR separately (thus providing faster feedback and thus allow
> > for
> > > > > >> faster integration).
> > > > > >>
> > > > > >> And while we are at it: Please keep in mind that new features
> > also require
> > > > > >> appropriate documentation. :-)
> > > > > >>
> > > > > >> Thanks and best regards,
> > > > > >> Karli
> > > > >
> > > >
> > > >
> > >
> >
> >
>
More information about the petsc-dev
mailing list