[petsc-dev] Target next PETSc/TAO release for March 30
Munson, Todd
tmunson at mcs.anl.gov
Fri Mar 23 18:46:52 CDT 2018
The next milestone that includes a PETSc release is due on
September 30, 2018. Consider yourself warned. :)
Todd.
> On Mar 23, 2018, at 12:21 PM, Jed Brown <jed at jedbrown.org> wrote:
>
> I think it's feasible, but are we ever going to have more than a week's
> notice so that we can have a known merge window followed by a few days
> of feature freeze?
>
> Richard Tran Mills <rtmills at anl.gov> writes:
>
>> All,
>>
>> To meet deliverables for one the DOE projects providing major funding for
>> PETSc development, Barry, Todd, and I agree that we should target Friday,
>> March 30 for the next PETSc/TAO release.
>>
>> Does anyone see any major obstacles to this? Does anyone have anything that
>> will require some extra help/coordination?
>>
>> Thanks,
>> Richard