Access Grid
Rick Stevens
stevens at mcs.anl.gov
Fri Jul 23 16:47:48 CDT 1999
I'd like to add my two cents. We really need some NCSA help to get
the ACCESS-DC Center up to spec particularly if we are going to originate
source from there during the Chautauquas. I've heard that Rita might
be willing to give a talk from ACCESS-DC. We dont have extra Gear to
send, but we can send some people to install and test gear etc.
Thanks
--Rick
At 02:26 PM 7/23/99 , Mark Hereld wrote:
>All --
>
>Startlingly few days remain before the first Chautauqua at which, according
>to our original plan, 6 leading edge Access Grid sites would have at least
>one each Access Grid Nodes up and running while one of three Chautauqua
>sites hosted a distributed meeting with much Fanfare and Hooha. In very
>broad brush stroke, the situation is as follows: Leading Edge Access Grid
>Sites 1 (ANL, full compliance) and Chautauqua sites 2 (UKY and UNM, each at
>better than half compliance). Time to play catch up. We are well past time
>to order hardware. It should all be in and installed, or nearly so. You
>should also be fully functional in the installation, care, feeding, and
>effective use of a number of tools... as well as fully engaged in the
>backchannel communications needed to keep an interactive distributed meeting
>flowing and going. By now each Access Grid node should have:
>
>(*) two to three AG technicians to handle AG node operation
>
>(*) linux box for video capture w/boards
>(*) linux box for audio capture w/boards
>(*) NT box for display w/boards
>(*) Win98 box for control
>(*) networked
>(*) mbone enabled
>(*) echo cancel gear (either 3 box, or new-fangled 1 box solution)
>(*) cables
>(*) 3 projectors
>(*) real estate
>(*) 3 cameras
>(*) 3 mics
>
>(*) vic, rat, etc. -- latest copies installed, configured
>(*) mud installed and expertly used
>(*) echo cancellation gear configuration
>
>(*) distributed power point (dPPT)
>(*) video resource manager -- downloaded, installed, configured, running
>(*) multicast beacon -- downloaded, installed, second nature
>
>Score 1 point for each (*) that you have under your belt. If you scored
>less than 15 out of 19, then you are holding up the progress of the Access
>Grid and in danger of having your license revoked. You get the idea.
>
>Many of you have very little of the prescribed hardware in hand. Many more
>of you haven't downloaded or installed much of the AG specific code, tools,
>and glue.
>
>-- Mark and Terry
>
>
More information about the ag-tech
mailing list