I think using coasters direct to PBS would be a good approach for you to 
try. Your jobs will finish fast and send their data back. Im no sure if 
the Swift engine itself will exit when all the jobs are done, or if it 
will wait for the coaster-worker PBS jobs to terminate. Even if so, that 
should still enable you to do a lot of productive workflow testing and 
experimentation. You'll know all the jobs are done from the progress 
report on stdout.

On 3/19/09 4:49 PM, Andrew Boyce wrote:
> So I was right. OK. I suppose there isn't much I can do about that, 
> besides change my provider configuration/use another provider/change 
> keep_completed?