itaps-parallel TO DO list for ITAPS review
Lori A. Diachin
diachin2 at llnl.gov
Fri Mar 6 19:14:58 CST 2009
Hi All,
My apologies if you get this email more than once from the various email
lists - I'm no longer sure who is on which one and want to be sure I have
complete coverage (perhaps I could create a new email list called itaps-all
:-) ).
While on the first leg of my trip home from CSE09 I had plenty of time to
devise our schedule of events to prepare for the review. I've included
below fairly aggressive timelines for updating/testing our software (note
the threatened bootcamp!), writing our review document, updating our web
pages, and preparing for the review presentation. I am hopeful that there
is not too serious an overlap on writing the review document and the
software as both of those activities will take some serious effort over the
next 3-4 weeks.
Feel free to print this out and post it near your computer so that you can
be inspired!
Lori
TO DO before the review
----------------------------
Software
-----------------
Expected Primary Participants:
Jason, Vitus, Ting, Onkar, Martin, Mark M, Ryan, Harold, Carl (if possible)
Expected Secondary Particpants:
Carl, Tim, Lori, Karen, Xiaolin
March 10-12 Telecon to finalize iMesh.h for next release
March 15 iMesh.h documentation finalized and released
March 18 - Telecon to discuss iMesh update progress
March 20 - iMesh implementations updated and finalized
March 23 - Telecon to discuss services update -
March 23 - Decision on Bootcamp necessity
March 25 - iMesh implemetnations tested by all; tarballs updated to web page
March 26 - Services updated
March 30 - Telecon to discuss Services update and testing
March 30 - Software web pages updated; documentation of iMesh; services;
tutorial
April 3 - Services tested by all against implementations
April 6-8 - Hold for possible boot camp if remote work doesn't go well
April 7 - Services tarballs updated to the web page
Review Document
-----------------
Expected Primary Participants:
Lori, Karen, Mark, Tim, Roman, Xiaolin, Ken, Harold, Ahmed, Carl
March 6 Outline distributed to everyone (Lori)
March 8 Document repository created
March 8 Latex structure in place
March 9-10 Telecon to discuss Outline (All)
March 10 Collaboration letters drafted and requested of app partners
March 13 First draft of all primary materials due (All)
March 16 First draft of edited document text (distributed by Lori)
March 18 Telecon to discuss document (All)
March 18 Draft of review questions answered
March 20 Milestones and deliverables Table (All)
March 20 Institutional milestones (1 page bulleted list each)
March 20 Collaboration letters due to Lori
March 23 Final draft of review document distributed
March 24 Final feedback due (morning)
March 25 Review Document Due (All)
Web pages
-----------------
Expected Primary Participants:
Lori
Expected Secondary Partipants:
Karen, Mark, Tim, Roman, Xiaolin, Ken, Harold, Ahmed, Carl
March 8 First draft of revised web pages based on SciDAC review article
March 18 Update of web pages based on proposal material
March 18 Update of presentations/publications list
March 30 Software web pages updated; documentation of iMesh; services;
tutorial
Review Presentation
---------------------
Expected Primary Participants:
Lori, Karen, Mark, Tim, Roman
Exptected Secondary Participants:
Xiaolin, Ken, Harold, Ahmed, Carl
March 25 Review Document Due (All)
April 10 First draft of Review slides
April 15 Knowledge of reviewers obtained
April 17 Revision of review slides
April 21 Dry Run in DC (Lori, Mark, Tim, Karen, Roman)
April 22 Review in DC (Lori, Mark, Tim, Karen, Roman)
More information about the itaps-parallel
mailing list